Quantitative Project Management using PERT Analysis

Task A

1. Determine the expected completion time for each of the nine project activities.

The PERT equation used in calculation of the expected time as illustrated by Chemuturi & Cagley (2010) is =

E = (O + 4M + P)/6, where

O= optimistic value

M= probability time value

P=pessimistic time value

E= expected time value

From the above formula, the paper used it in calculating the expected time values listed in the table in the embedded excel workbook (double click on the icon “Students_Task_4Vl_MF6_15”). An example of calculation for A is below:

E = (O + 4M + P)/6, where

O=2, M =3.1, P=3.6

E= (2+4(3.1) +3.6)/6

E=3

2. Determine the variance for each of…

🔒

You're reading 150 of 1,693 words

Unlock the full essay and 2,000+ other essays for just $2.
Access is valid for 30 days.

✔ 30-day unlimited access ✔ 2,000+ essays ✔ Instant unlock after payment

✍️ Need a Similar Essay on Project Management?

Our expert writers craft 100% original, zero-AI, plagiarism-free essays on any topic. Any length, any deadline.

✅ 100% Human Written ✅ 0% AI Plagiarism ✅ Turnitin Safe ✅ Free Plagiarism Report ✅ On-Time Delivery ✅ Money-Back Guarantee
🎓 Order a Custom Project Management Essay Now